|
| |
 |
 |
|
|
|
Canals to Drain
Lake Mattamuskeet |
|
|
|
he
plan to drain Lake Mattamuskeet originally called for a network of 83
miles of drainage and light transportation canals to bring the lake water
to the pumping plant and channel it to the Pamlico Sound, at a dredging
cost of $266,965. The Drainage Commissioners awarded A. V. Wills &
Sons of Pittsville, IL, a dredging contract that called for excavating
3,100,000 cubic yards of soil.
|
|
|
|
|
A.
V. Wills & Sons had four steam-powered dipper dredges built for the
job at Belhaven, NC, about thirty miles west of the lake. The dredge boat
crews lived on board and the boats had lights that permitted 24-hour
dredging operations. Small gasoline-powered skiffs pulled coal barges to
the dredge boats to supply fuel for the steam engines and water barges to
supply clean fresh water for the boilers.
Work
began in April 1914 on the north shore of the Pamlico Sound, seven miles
due south of the proposed pumping plant, with the objective of dredging a
large navigable canal to the site of the proposed pumping plant. This
canal would provide access to the lake for large boats and barges to
transport the necessary building material for the pumping plant and would
be the main outlet for the fresh lake water to be drained into the Pamlico
Sound. The canal was 70 feet wide at the top and 60 feet wide at the
bottom and was named “Outfall Canal”. The contractor completed this
canal, which involved excavating 754,000 cubic yards or virgin earth,
trees, roots, and stumps, in just eight months.
Having
completed Outfall Canal, the dredges moved into the lake, and dredged 76
more miles of canals in the lake bed to bring the water to the pumping
plant. The plan called for a “West Main Canal” and an “East Main
Canal” running from the northern end of Outfall Canal to the west and
east ends of the lake and a series of nine north-south canals extending
from these main canals entirely across the lake on a north-south line.
Each canal was elevated to allow the natural flow of water from the
farthest point to the pumping plant which was built on the south-central
shore of the huge body of water.
It
quickly became evident that the original dredging plan was inadequate to
drain all of the lake, so the Commissioners amended the dredging contract,
expanding the plan to 130 miles of canals. The contractor completed the
revised dredging contract in early 1919.
For the duration of
the drainage project, which lasted through 1932, it was necessary for
dredges to operate continuously to maintain the canals and remove silt
washed in from the lake bed. Several companies performed this work under
subsequent contracts.
|
|
|
|
 |
|